Work on Coastal Gaslink project nears completion
PRINCE GEORGE — It was a productive summer when it comes to work on the Coastal Gaslink project.
The company says pipe installation has reached 97 per cent with what its calling “incredible progress” this summer.
Coastal Gaslink says a number of “significant milestones have been achieved this summer,” including:
- 100% pipe install in Section 2 – With the recent completion of all pipe installation in Section 2, Coastal GasLink has now completed pipe install in four sections, including Sections 1, 2, 4 and 6.
- All major water crossings are now complete – Coastal GasLink completed its final of ten major trenchless water crossings. The Morice River crossing was completed using micro-tunnelling, the most technologically advanced forms of trenchless crossing, ensuring the environment and valued water resources were protected.
- Hydrotesting is 91% complete – Hydrotesting represents one of the final stages of pipeline construction, and ensures that the pipe is ready to safely receive natural gas