CGL Pipeline: Construction complete

Nov 30, 2023 | 3:48 PM

Northern BC – Coastal GasLink has achieved 100% pipe installation across the entire project route, connecting northeastern B.C. to LNG Canada’s facility on the west coast.

This means that all 670 kilometres of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled. From the Wilde Lake Compressor Station near Dawson Creek to our Metering Station in Kitimat, physical construction on the project is now complete.