Pipeline construction hampered by hearings, permits, court action: report
VANCOUVER — A report from environmental group Stand.earth says it expects construction of the Trans Mountain pipeline expansion to be delayed by detailed route hearings, outstanding provincial permits and Indigenous court challenges.
The Canadian Energy Regulator, formerly the National Energy Board, revoked all previous route approvals in July and required Trans Mountain Corp. to file new notices of its proposed route.
Residents, municipalities and Indigenous groups may then file statements of opposition and the energy regulator decides on a segment-by-segment basis whether to hold detailed route hearings.
The report says statements of opposition have been filed in every major segment and hearings are likely to be considered for the Fraser River crossing, Burnaby Mountain Tunnel, and areas where schools, homes and municipal water supplies could be affected.